News update new factory 25/03![]() View of the factory The installation of the wall PUF panels of the main shed is almost finished whereas the brick work, plumbing, flooring and plastering of the office block as well as the staff quarters are on the verge of completion. The security post and the utility block will be ready for the first roof slab by the end of this month. The electrical connection with 309 kilowatts at the site is ready to be installed this week. The preparations are on for the outdoor flooring, roads, drainage and sewage. The project seems to have delayed by almost a month because of untimely rains and festivals in between. |
|