News update from the new factory construction

Maheshwar Dutt Sharma
CEO India
26 February 2015
Source / Author: Maheshwar Dutt Sharma
26 February 2015
Inside the building
Inside the building

News update from the new factory construction

The flooring and PUF roofing of the manufacturing area is over. The grooving work on the industrial flooring is in progress. The central partition wall is being erected out of profile sheets in off-white colour. The second floors of the office block and the staff quarters in RCC are also completed. The plastering of the RCC construction is on the verge of completion whereas the flooring of these sections is about to start.
Roof
Roof

The excavation of foundation for the security post, electric meter room, generator room etc. is in progress. Plumbing of the staff quarters is going on. PCC electric poles and the heavy duty cable for the 309 Kilowatt connection are at site.

The outside roads, front railing, main gate, wall PUF panels and sewerage etc. are being executed as planned. The factory will be operational by the end of April, 2015.