Construction update 22-07-2015

Maheshwar Dutt Sharma
CEO India
22 July 2015
Source / Author: Maheshwar Dutt Sharma
22 July 2015
Electrical department
Electrical department

Construction update 22-07-2015

The electrical section is now shifted to the new campus and the electrical workshop is being set up to be operational. Electrification of the two production halls is over. Shifting of stores and inventory is in progress. The marketing section is partly shifted to the new campus as well.

First stock
First stock
The internet connection from BSNL is in place and the tower for additional “Connect” broadband is also installed.

The gutters, vertical drains and flashings of the main building are on the verge of completion.

The staff quarters will now be ready for use by August 06, 2015 due to interruption of work by Monsoon rains. Fixing of doors, insulation of the roof and setting up of kitchen and toilets are the jobs that remain unfinished.

Fixing of UPVC windows of the main building is over but the doors of the staff quarters are yet to be fixed.

Plastering of the boundary wall and the inside of the first floor of the office block are in progress.  

Construction of the loading dock and the PCC flooring of the outside area are now in progress. The road around the building and the floor tiles are also in progress after the rains stopped for a few days.