Construction update 08-06-2015

Maheshwar Dutt Sharma
CEO India
08 June 2015
Source / Author: Maheshwar Dutt Sharma
08 June 2015
View from a distance
View from a distance

Construction update 08-06-2015

The main building is now closed from all sides by the wall panels. The roofs of the canopies are also done. The gutters, vertical drains and flashings will start this week to complete the panel work by June 15, 2015.
Construction update 08-06-2015

The installation of automatic overhead doors is on the verge of completion and expected to be done by June 14, 2015.

The staff quarters are now ready with plumbing, electrification, flooring and painting except for insulation of the roof and tiling and fitting of bathrooms and kitchen that will start in a couple of days. The roof of the staff quarters is being insulated with bitumen, clay and brick tiles.

The loading dock is under construction and the septic tanks are already finished. It will take about two weeks when the outside floor area will be ready for PCC and tiles after the damaged walls are redone.

The underground drain pipes are laid around the building till the main outlet. The boundary wall on the backside of the building is being redone for extra strength after it was observed tilting outwards.

The fire audit of the building has been done by the concerned government department with the recommendations for the size of the hydrant needed and the quantity of fire extinguishers to be placed.

We look forward to start shifting to the new factory from Aug 01, 2015.