Construction update 05-2015

Maheshwar Dutt Sharma
CEO India
06 May 2015
Source / Author: Maheshwar Dutt Sharma
06 May 2015
Paint
Paint

Construction update 05-2015

The installation of automatic overhead doors has been started today by the team from Metaflex. The staff quarters are being given a finishing touch after plumbing, electrification, flooring and painting jobs coming to the completion.

Transformator
Transformator
The electric transformer and main cables are in place and await the supply from the source that will start from June 01, 2015.

Levelling of the outside area of the building is on the verge of completion after the slabs on the septic tanks were finished last week. The loading dock is in the advanced stage of completion.

Digging of the trenches for the outside underground drains has been started and all the pipes and fittings are ordered. The extra PUF panels and gutters are also ordered to finish the roof and walls of the main shed.

We look forward to start shifting to the new factory from July 01, 2015.