Construction update 01-07-2015![]() Outside view Construction update 01-07-2015The 400 volts, 3 phase power connection with 309 kilowatts has been installed at the factory premises. Two BSNL landline telephone connections with STD and internet are also sanctioned. An additional broadband internet connection with 2 mbps speed has been applied for.
![]() Staff quarters The gutters, vertical drains and flashings of the main building are now being fixed. The installation of automatic overhead doors is complete.
The staff quarters will be ready for use by July 15, 2015 after the roof is insulated and the doors fixed. The UPVC windows of the main building are now being fixed and expected to be done by July 7, 2015. The PCC flooring of the outside area is in progress. The road around the building and the floor tiles are next to be started soon. Shifting of some stocks and capital machinery has been started gradually to be prepared to enter the new campus in August, 2015. |
|